We scheduled the fireplace install for Monday after quite an ordeal with our installer. We are waiting for our stone until after the final paint.
Drywall is supposed to take a week. Our columns and dining room header will be fixed. The broken bathroom window will be replaced, and the in-wall dryer vent installed.
Next week, our excavator will be trenching the waterline in freakishly cold temperatures. The shakes & siding will be finished; They are three weeks behind. Friday, we are supposed to be primed and the following week will be our final paint.
The following week, cabinets & counters will be installed.
On the 30th, the plumber will hook up all of our fixtures and lines.
After the new year, they will install flooring and will do touch-ups. We are supposed to get the keys January 10th. That's sad, but oh well. We still love our house!