Thursday, December 5, 2013

Updates - Day 86

Our attic and garage ceiling insulation was blown today and the drywall finishers  taped and mudded seams. We met with our Field Manager and he updated us with our timeline. Our projected date was December 20th. Our actual date is now January 10th. 

We scheduled the fireplace install for Monday after quite an ordeal with our installer. We are waiting for our stone until after the final paint. 

Drywall is supposed to take a week. Our columns and dining room header will be fixed. The broken bathroom window will be replaced, and the in-wall dryer vent installed.

Next week, our excavator will be trenching the waterline in freakishly cold temperatures. The shakes & siding will be finished; They are three weeks behind. Friday, we are supposed to be primed and the following week will be our final paint. 

The following week, cabinets & counters will be installed.

On the 30th, the plumber will hook up all of our fixtures and lines. 

After the new year, they will install flooring and will do touch-ups. We are supposed to get the keys January 10th. That's sad, but oh well. We still love our house! 