Sunday, November 17, 2013

Rough timeline - Day 68

After a huge week at our home and a meeting with the Field Manager ( who is fantastic), this is the rough run to the finish line:
11/17 - fix framing of fireplace
11/18 - framers fix garage lip, concrete, drywall delivered
11/25 - Start drywall finish 
12/6-7 - ready to paint, cabinets delivered
12/10 - Counters & Trim 
12/16 - laminate vinyl
12/17 - carpet
12/20 - Merry Christmas from Wayne Homes if everything works out correctly! 


4 comments:

  1. When are they doing the siding? What color did you choose?

    ReplyDelete
  2. We aren't sure. They said the siding crews are the ones that are the most backed up! They would ideally like to side when they drywall, but I'm not sure that is going to happen.

    ReplyDelete
  3. I hope everything falls into place so you can have the best Christmas present ever.

    ReplyDelete
  4. We chose Tuscan Clay siding (which we got in the "upgraded" siding, although I don't remember what it's called) and harvest cedar shakes.

    ReplyDelete