Tuesday, November 5, 2013

Maybe? -Day 56

We were told yesterday that the framers might come out and do some work - like fix the fireplace (paid for 2x6 construction, but built with 2x4 construction). This isn't a big deal because we caught it in time and we were assured it would be fixed. No one showed, though. So, we are hoping some work gets done today. After a phone call with our project manager yesterday morning, the plan is to finish framing by Friday. Shingles will be delivered Monday and they will start the roof. Our project manager says he is really pushing to hand the keys over to us by December 20th, which would be great for many reasons...we are crossing our fingers.